JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,290,000. JRE2 recognizes revenue upon contract completion. Cost incurred Estimated Cost to Complete 2017 $ 262,000 $ 1,610,000 2018 1,660,000 560,000 2019 510,000 0 In 2018, JRE2 would report gross profit (loss) of:

+1
Answers (1)
  1. 29 August, 12:41
    0
    Answer:loss of $192,000

    Explanation:

    Fixed Price = $2,290,000

    Cost Incurred=

    2017=$262,000

    2018=$1,660,000

    2019 = $510,000

    Estimated Cost to Complete=

    2017 = $1,610,000

    2018 = $560,000

    2019=0

    In 2018;

    first we add cost incurred from 2017 to 2018 to the estimated cost to complete for only 2018 giving us

    $262,000 + $1,660,000 + $ 560,000 = $2,482,000

    and then subtract it from fixed price;

    $2,290,000 - $2,482,000 = - $192,000

    ie $ (192,000) gross loss.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,290,000. JRE2 recognizes revenue upon contract completion. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.