Ask Question
15 April, 07:02

The amount of increase or decrease in cost that is expected from a particular course of action as compared with an alternative is termed: Group of answer choices period cost product cost differential cost discretionary cost

+3
Answers (1)
  1. 15 April, 09:42
    0
    differential cost

    Explanation:

    When you are elaborating a differential cost analysis between two alternative projects or actions, you are looking for the difference in total costs between both alternatives.

    For example, you might elaborate a cost analysis to decide whether to continue or stop the production of a certain good. What are the costs associated with stopping the production versus thee profitability of continuing the production.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The amount of increase or decrease in cost that is expected from a particular course of action as compared with an alternative is termed: ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.