At Mahlon Company, a manufacturer of boats, indirect labor is a variable cost that varies with direct labor-hours. Last month's performance report showed that actual indirect labor cost totaled $5,780 for the month and that the associated spending variance was $245 F. If 24,100 direct labor-hours were actually worked last month, then the flexible budget cost formula for indirect labor must be (per direct labor-hour) :

+3
Answers (1)
  1. 4 April, 11:45
    0
    The flexible budget cost formula for indirect labor must be (per direct labor-hour) is $0.25

    Explanation:

    For computing the direct labor hour rate, we have to use the formula which is shown below

    = (Actual indirect labor cost + favorable associated spending variance):

    total direct labor hours

    where,

    Actual indirect labor cost is $5,780

    Favorable associated spending variance is $245

    And, the total direct labor hour is $24,100

    Now put these values to the above formula

    So, the answer would be equal to

    = ($5780 + $245) : 24,100 hours

    = $6,025 : 24,100 hours

    = $0.25

    Since the variance comes in favorable so we added in the actual indirect labor cost.

    Hence, the flexible budget cost formula for indirect labor must be (per direct labor-hour) is $0.25
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “At Mahlon Company, a manufacturer of boats, indirect labor is a variable cost that varies with direct labor-hours. Last month's performance ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.