The Jase Company allocates overhead based on a predetermined overhead rate of $9.00 per direct labor hour. Job J904 required 8 tons of direct material at a cost of $600 per ton and took employees who earn $21 per hour a total of 80 hours to complete. What is the total cost of Job J904?

+4
Answers (1)
  1. 4 August, 09:12
    0
    The total cost of job J904 = $7,200

    Explanation:

    Direct material cost = 8 tons * $600 / ton = $4,800

    Direct labour cost = 80 hours * $21 / hour = $1,680

    Overhead cost = 80 hours * $9 / hour = $720

    Total = $7,200
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The Jase Company allocates overhead based on a predetermined overhead rate of $9.00 per direct labor hour. Job J904 required 8 tons of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.