Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. Design modification costs of $155,000 are based on number of design changes. Jackson Company has identified 40,000 batches and has 5,000 design changes in their factory. What is the activity rate for setup?

+1
Answers (1)
  1. 26 October, 22:53
    0
    Answer:52.25
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Jackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.