A factory produces 130,000 televisions per quarter. A total of 9,000 production hours are used by the factory per quarter.

Compute the velocity in units per hour.

(Note: Round answer to two decimal places.)

a. 16.50 units per hour

b. 15.50 units per hour

c. 14.44 units per hour

d. 18.45 units per hour

+3
Answers (1)
  1. 18 June, 11:12
    0
    Option (c) is correct.

    Explanation:

    Given that,

    Factory produces = 130,000 televisions per quarter

    Total production hours used by the factory per quarter = 9,000

    Therefore,

    Velocity of units per hour = (Number of units produced : Time taken to produce those units.)

    Velocity of units per hour = (130,000 units : 9,000 hours)

    Velocity of units per hour = 14.44 units per hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A factory produces 130,000 televisions per quarter. A total of 9,000 production hours are used by the factory per quarter. Compute the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.