Ask Question
4 July, 16:12

The following information has been gathered for Foxmoor Industries for its fiscal year ending December 31: Estimated factory overhead costs $ 2,496,000 Actual factory overhead costs $ 1,812,400 Estimated labor hours 78,000 Actual labor hours 81,700 Estimated labor costs $ 771,000 Actual labor costs $ 855,125 Estimated machine hours 111,000 Actual machine hours 117,600 What is the predetermined factory overhead rate per labor hour?

+1
Answers (1)
  1. 4 July, 17:14
    0
    Estimated manufacturing overhead rate = $32 per labor hour

    Explanation:

    Giving the following information:

    The estimated factory overhead costs $ 2,496,000. Estimated labor hours 78,000.

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 2496000/78000 = $32 per labor hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following information has been gathered for Foxmoor Industries for its fiscal year ending December 31: Estimated factory overhead costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.