Which of the following should be considered when a company estimates the cash flows used to analyze a proposed project?

a. The firm would borrow all the money used to finance the new project, and the interest on this debt would be $1.5 million per year.

b. The company spent and expensed $10 million on a marketing study before its current analysis regarding whether to accept or reject the project.

c. The company has spent and expensed $1 million on research and development costs associated with the new project.

d. Since the firm's director of capital budgeting spent some of her time last year to evaluate the new project, a portion of her salary for that year should be charged to the project's initial cost.

e. The new project is expected to reduce sales of one of the company's existing products by 5%.

+4
Answers (1)
  1. 11 March, 14:58
    0
    e.

    Explanation:

    The new project is expected to reduce sales of one of the company's existing products by 5%.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following should be considered when a company estimates the cash flows used to analyze a proposed project? a. The firm would ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.