When auto manufacturer BMW purchased the RollsminusRoyce brand name, BMW had to hire and train a new staff of assembly workers. The new workers were paid $ 23.00 per hour, worked a total of 7 comma 000 hours, and produced 1 comma 600 cars. BMW budgeted for a standard labor rate of $ 28.00 per hour and 3.25 direct labor hours per car. What is the direct labor efficiency variance for the RollsminusRoyce division? A. $ 50 comma 400 favorable B. $ 50 comma 400 unfavorable C. $ 41 comma 400 unfavorable D. $ 41 comma 400 favorable Click to select your answer.

+5
Answers (1)
  1. 8 November, 14:00
    0
    B. $ 50 comma 400 unfavorable

    Explanation:

    The formula to compute the labor efficiency variance is shown below:

    = Standard labor rate * (Standard hours for actual output - Actual hours)

    where,

    Standard labor rate is $28

    Standard hours for actual output would be

    = 1,600 cars * 3.25 direct labor hours per car

    = 5,200 hours

    And, the actual hour is 7,000 hours

    Now put these values to the above formula

    So, the value would equal to

    = $28 * (5,200 hours - 7,000 hours)

    = $50,400 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “When auto manufacturer BMW purchased the RollsminusRoyce brand name, BMW had to hire and train a new staff of assembly workers. The new ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.