The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,260. A total of 37 direct labor-hours and 141 machine-hours were worked on the job. The direct labor wage rate is $13 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost for the job on its job cost sheet would be:$3,259$2,741$4,715$2,287

+1
Answers (1)
  1. 11 November, 21:59
    0
    The correct answe is $4715

    Explanation:

    First, we need to accommodate the information provided:

    Job 323:

    direct materials = $2260

    direct labor hours = 37

    machine hours = 141

    The cost of direct hours is $13. Based on a predetermined overhead rate, machine hours cost $14.

    Total cost for the job = 2260 + 37*13 + 141*14

    Total cost for the job = $4715.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,260. A total of 37 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.