Which capital budgeting method is most useful for evaluating a project that has an initial afterminustax cost of $5,000,000 and is expected to provide afterminustax operating cash flows of $1,800,000 in year 1, ($2,900,000) in year 2, $2,700,000 in year 3, and $2,300,000 in year 4?

+2
Answers (1)
  1. 19 April, 16:22
    0
    (NPV) Net present value method is the most effective capital budgeting method

    Explanation:

    we know here

    initial after minus tax cost = $5,000,000

    after minus tax cash flows in 1st year = $1,800,000

    and in 2nd year = $2,900,000

    and in 3rd year = $2,700,000

    and 4th year is = $2,300,000

    so here cash outflows even after the initial outlay in year 0

    so we not use here IRR

    so that best and most most effective capital budgeting method is NPV net present value

    we use it NPV
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which capital budgeting method is most useful for evaluating a project that has an initial afterminustax cost of $5,000,000 and is expected ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.