Two alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below. Alternative X Alternative Y Materials costs $ 41,000 $ 59,000 Processing costs $ 45,000 $ 45,000 Equipment rental $ 17,000 $ 17,000 Occupancy costs $ 16,000 $ 24,000 Are the materials costs and processing costs relevant in the choice between alternatives X and Y? Multiple Choice Neither materials costs nor processing costs are relevant Only processing costs are relevant Only materials costs are relevant Both materials costs and processing costs are relevant

+5
Answers (1)
  1. 24 October, 21:17
    0
    The correct answer is C.

    Explanation:

    Giving the following information:

    Costs associated with the alternatives are listed below.

    Alternative X

    Materials costs $ 41,000

    Processing costs $ 45,000

    Equipment rental $ 17,000

    Occupancy costs $ 16,000

    Alternative Y

    Materials costs $ 59,000

    Processing costs $ 45,000

    Equipment rental $ 17,000

    Occupancy costs $ 24,000

    Only Material Costs are relevant because they vary whether you chose Alternative X or Y. Processing costs are the same in both options.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Two alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.