Critical Chain Project Management (CCPM) attempts to keep the most highly demanded resource busy on critical chain activities, but not overloaded. True/false

+2
Answers (1)
  1. 31 May, 04:09
    0
    True

    Explanation:

    Critical Chain Project Management (CCPM) is referred to as the approach that works for project completion and managing. it includes the effective use of resources like people, equipment, etc.

    steps include in Critical Chain Project Management (CCPM) are:

    1) determine critical chain

    2) estimate the resource constraints

    3) focus your team

    4) use single-tasking

    5) estimate time for a particular task

    6) check for changes, provides alternate for any change

    7) present the project report
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Critical Chain Project Management (CCPM) attempts to keep the most highly demanded resource busy on critical chain activities, but not ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.