Sometimes the risks posed by a project are deemed unacceptably large compared to the potential benefits, and the ultimate avoidance strategy is to not perform the project at all. (True/False)

+3
Answers (1)
  1. 29 May, 06:02
    0
    True.

    Explanation:

    In assessment of risk, a firm can employ the use of cost benefit analysis to determine it risk acceptability or avoidance. This can simply be explained as; if the cost of accepting the risk is higher than the benefit/returns from such risk the project is deemed to be rejected.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sometimes the risks posed by a project are deemed unacceptably large compared to the potential benefits, and the ultimate avoidance ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.