Barr Corp. started a long-term construction project in 20X0. The following data relate to this project: Contract price $4,200,000 Costs incurred in 20X0 $1,750,000 Estimated costs to complete $1,750,000 Progress billings $900,000 Collections on progress billings $800,000 The project is accounted for by the percentage of completion method of accounting. In Barr's 20X0 income statement, what amount of gross profit should be reported for this project?

+4
Answers (1)
  1. 1 October, 04:26
    0
    The correct answer is $350,000

    Explanation:

    Contract price = $4,200,000

    Costs incurred = $1,750,000

    Estimated costs to complete = $1,750,000

    Progress billings = $900,000

    Collections on progress billings = $800,000

    Contract price - total estimated cost

    $4,200,000 - ($1,750,000 + $1,750,000)

    = $4,200,000 - $3,500,000

    = $700,000

    one-half of the estimated costs of this construction project were incurred

    $1,750,000 : ($1,750,000 + $1,750,000)

    = $1,750,000 : $3,500,000

    = 0.5

    In Barr's 20X0 income statement, what amount of gross profit should be reported for this project?

    $700,000 x 0.5 = $350,000

    $350,000 should be reported as gross profit for the 20X0 income statement.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Barr Corp. started a long-term construction project in 20X0. The following data relate to this project: Contract price $4,200,000 Costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.