Ask Question
18 August, 14:39

Project A has an initial cost of $80,000 and provides cash inflows of $34,000 a year for 9) three years. Project B has an initial cost of $80,000 and produces a cash inflow of $114,000 in year 3. The projects are mutually exclusive. Which project (s) should you accept if the discount rate is 11.7 percent? What if the discount rate is 13.5 percent?

+2
Answers (1)
  1. 18 August, 14:54
    0
    Complete question:

    Project A has an initial cost of $80,000 and provides cash inflows of $34,000 a year for three years. Project B has an initial cost of $80,000 and produces a cash inflow of $114,000 in year 3. The projects are mutually exclusive. Which project (s) should you accept if the discount rate is 11.7 percent? What if the discount rate is 13.5 percent?

    A. Accept A as it always has the higher NPV.

    B. Accept B as it always has the higher NPV.

    C. Accept A at 11.7 percent and B at 13.5 percent.

    D. Accept B at. 11.7 percent and A at 13.5 percent.

    E. Accept A at 11.7 percent and neither at 13.5 percent.

    Answer:

    Accept A at 11.7 percent and neither at 13.5 percent.

    Solution:

    Using a financial calculator to solve the problem:

    For project A with a discount rate of 11.7%

    Outlay = 80,000

    CF for year 1 = 34000

    CF for year 2 = 34000

    CF for year 3 = 34000

    I = 11.7 %

    NPV = 2085

    For project A with a discount rate of 13.5%

    Outlay = 80,000

    CF for year 1 = 34000

    CF for year 2 = 34000

    CF for year 3 = 34000

    I = 13.5%

    NPV = - 397.5

    For project B with a discount rate of 11.7%

    Outlay = 80,000

    CF for year 1 = 0

    CF for year 2 = 0

    CF for year 3 = 114,000

    NPV = 1798

    For project B with a discount rate of 13.5%

    Outlay = 80,000

    CF for year 1 = 0

    CF for year 2 = 0

    CF for year 3 = 114,000

    NPV = - 2,032

    From the above calculations, Accept A at 11.7 percent and neither at 13.5 percent.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Project A has an initial cost of $80,000 and provides cash inflows of $34,000 a year for 9) three years. Project B has an initial cost of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers