An activity being analyzed under PERT was judged to most likely have a duration of 40 days. When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 days and even under the worst case imaginable, the task would be take 50 days. The estimates PERT duration of that activity is:
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “An activity being analyzed under PERT was judged to most likely have a duration of 40 days. When considering the time it would take to ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.