Ask Question
13 March, 13:19

The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,057. A total of 37 direct labor-hours and 194 machine-hours were worked on the job. The direct labor wage rate is $24 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $33 per machine-hour. The total cost for the job on its job cost sheet would be: a) $6,303 b) $6,722 c) $9,347 d) $11,492

+2
Answers (1)
  1. 13 March, 16:46
    0
    The correct answer is C.

    Explanation:

    Giving the following information:

    The direct materials = $2,057.

    Direct labor hours = 37

    Machine hours = 194

    The direct labor wage rate is $24 per labor-hour.

    The predetermined overhead rate is $33 per machine-hour.

    To calculate the total cost, we need to use the following formula:

    Total cost = direct material + direct labor + allocated overhead

    Direct labor = 37*24 = $888

    Allocated overhead = 33*194 = $6,402

    Total cost = 2,057 + 888 + 6,402 = $9,347
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,057. A total of 37 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers