Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $900,000. The contract price was $1,300,000. Costs of the contract for 2018, the first year, totaled $675,000.

a. What was the gross profit reported by the percentage of completion method for 2016?

b. After the contract was completed at the end of 2017 at a total cost of $950,000, what was the gross profit reported by the percentage of completion method for 2017?

+3
Answers (1)
  1. 24 September, 18:09
    0
    Answer for Part A and Part B is as follows:

    Particulars 2016 year 2017 year

    Contract Price $13,00,000 $13,00,000

    Cost that has been incurred $675000 $950000

    Estimated cost to complete $225000 $0

    TOTAL COST $900000 $950000

    Expected Gross profit $400000 $350000

    Percentage that is completed 75 percent 100percent

    Gross profit to be recognised $300000 $50000

    Note: Calculations have been made according to the data and figures given in the question.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $900,000. The contract price was ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers