Ask Question
27 June, 11:46

During the current year, Carlisle Manufacturing expected Job No. 16 to cost $450,000 of overhead, $750,000 of materials, and $300,000 in labor. Carlisle applied overhead based on direct labor cost. Actual production required an overhead cost of $420,000, $825,000 in materials used, and $330,000 in labor. All of the goods were completed. What is the amount of over - or under-applied overhead?

+3
Answers (1)
  1. 27 June, 15:32
    0
    Underapplied = $75000

    Explanation:

    Giving the following information:

    Carlisle Manufacturing expected Job No. 16 to cost $450,000 of overhead, $750,000 of materials, and $300,000 in labor.

    Carlisle applied overhead based on direct labor cost.

    Actual production:

    Overhead cost = $420,000.

    Direct materials = $825,000.

    Direct labor = $330,000.

    First, we need to calculate the overhead rate

    Overhead rate = 450000/300000 = 1.5 direct labor

    Overhead according to rate:

    330000*1.5 = $495000

    Real overhead = $420000

    Underapplied = $75000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “During the current year, Carlisle Manufacturing expected Job No. 16 to cost $450,000 of overhead, $750,000 of materials, and $300,000 in ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.