cost variance Tercer reports the following for one of its products. Direct materials standard (4 lbs. @ $2 per lb.) $ 8 per finished unit Actual finished units produced 60,000 units Actual cost of direct materials used $ 535,000 Compute the total direct materials cost variance and classify it as favorable or unfavorable.

+3
Answers (1)
  1. 3 April, 05:30
    0
    Total direct materials cost variance is $66,000 and it is favorable.

    Explanation:

    Actual cost = Actual Quantity * Actual Price

    = 300,000 * $1.78

    = $534,000

    Actual cost with selling price = Actual Quantity * Selling Price

    = 300,000 * $2.00

    = $600,000

    The total direct materials cost variance is computed as:

    Total direct materials cost variance = Actual cost with selling price - Actual Cost

    = $600,000 - $534,000

    = $66,000

    It is favorable.

    Working Note:

    Actual Price per lbs = $534,000 / 300,000

    = $1.78
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “cost variance Tercer reports the following for one of its products. Direct materials standard (4 lbs. @ $2 per lb.) $ 8 per finished unit ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.