In spring 2012, Mainline Engineering Company signed an $80 million contract with the city of Duluth, to construct a new city hall. Mainline expects to construct the building within two years and incur expenses of $60 million. The city of Duluth paid $20 million when the contract was signed, $40 million within the next six months, and the final $20 million exactly one year from the signing of the contract. Mainline incurred $24 million in costs during 2012 and rest in 2013 to complete the contract on time. Using the percentage-of-completion method how much revenue should Mainline recognize in 2012?

+5
Answers (1)
  1. 8 February, 16:23
    0
    Mainline should recognize a revenue of $32 million in 2012.

    Explanation:

    percentage-of-completion method:

    Total Expenses = $60 million

    Expenses during the Year 2012 = $24 million

    Percentage of complition = 24/60

    = 40%

    Revenue can be recognised = $80 million*40%

    = $32 million

    Therefore, Mainline should recognize a revenue of $32 million in 2012.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In spring 2012, Mainline Engineering Company signed an $80 million contract with the city of Duluth, to construct a new city hall. Mainline ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers