If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.80, how fast can they be expected to finish all twelve units? 289 hours 18 hours 264 hours 316 hours

+4
Answers (1)
  1. 27 May, 18:24
    0
    Answer: 289hours.

    Explanation: Every project boils down to money. If you had a bigger budget, you could probably get more people to do your project more quickly and deliver more. That's why no project plan is complete until you come up with a budget. But no matter whether your project is big or small, and no matter how many resources and activities are in it, the process for figuring out the bottom line is always the same.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.80, how fast can ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers