Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $22 million. Construction costs incurred in the first year were $12 million and estimated remaining costs to complete at the end of the year were $13 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method?

+3
Answers (1)
  1. 24 December, 00:07
    0
    year-1

    Cotract price 22,000,000

    Cost to date (12,000,000)

    Further Estimated Cost (1,000,000)

    Margin 9,000,000

    Stage of Completion on the basis work completion

    SOC % 12/13 92.308%

    For the year ended Profit & loss

    Year-1

    Revenue 92.308% 20,307,692

    Cost of Sales (12,000,000)

    Gross profit 8,307,692
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $22 million. Construction costs incurred ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.