Haft Construction Co. has consistently used the percentage-of-completion method. On January 10, Year 3, Haft began work on a $3 million construction contract. At the inception date, the estimated cost of construction was $2,250,000. The following data relate to the progress of the contract:
Gross profit recognized at 12/31/Yr 3 $ 300,000
Costs incurred 1/10/Yr 3 through 12/31/Yr 4 1,800,000
Estimated cost to complete at 12/31/Yr 4 600,000
In its income statement for the year ended December 31, Year 4, what amount of gross profit should Haft report?
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Haft Construction Co. has consistently used the percentage-of-completion method. On January 10, Year 3, Haft began work on a $3 million ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » Haft Construction Co. has consistently used the percentage-of-completion method. On January 10, Year 3, Haft began work on a $3 million construction contract. At the inception date, the estimated cost of construction was $2,250,000.