ToyMax seeks to determine the number of Kanban containers needed to feed a newly established work cell. The cell requires 600 parts over an eight-hour day. Production lead time for the parts needed by the cell is 3 hours and the cell supervisor recommends a safety stock equal to 50% of the cell's daily production. Assuming a container size of 100 parts, how many containers are needed for the new cell?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “ToyMax seeks to determine the number of Kanban containers needed to feed a newly established work cell. The cell requires 600 parts over an ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.