A consulting firm has a predetermined overhead rate of $120 per labor hour. The Smith job required 5 hours to compete. The overhead cost applied to this job is $

+5
Answers (1)
  1. 1 August, 19:46
    0
    overhead cost = $600

    Explanation:

    given data

    overhead rate = $120 per labor hour

    time required = 5 hours

    to find out

    overhead cost

    solution

    we get here overhead cost that is express as

    overhead cost = overhead rate * time required ... 1

    put here value and we get

    overhead cost = $120 * 5

    overhead cost = $600
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A consulting firm has a predetermined overhead rate of $120 per labor hour. The Smith job required 5 hours to compete. The overhead cost ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.