The following debits (credits) appear in Axe Company's Work in Process inventory account for the month of March: balance - $2,000; direct materials - $12,000; direct labor - $8,000; manufacturing overhead - $6,400; to finished goods - ($24,000). Axe applies overhead to jobs at a predetermined rate of 80% of direct labor cost. Job No. 9, the only job still in process at the end of March, has been charged with direct labor of $1,000. The amount of direct materials charged to Job No. 9 was:A) $12,000. B) $4,400. C) $2,600. D) $1,500.

+2
Answers (1)
  1. 4 May, 23:13
    0
    B) $4,400.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The following debits (credits) appear in Axe Company's Work in Process inventory account for the month of March: balance - $2,000; direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.