Bryant Company designs and builds fancy dining room tables for individual customers. On July 1, there were two jobs in process: Job 391 with a beginning balance of $21,700 and Job 392 with a beginning balance of $8,790. Overhead costs are applied by using a rate of 70% of direct labor costs. Both jobs are unfinished on July 31. Data on July costs for both jobs are as follows:Job 391Job 392Direct materials$5,100$ 9,200Direct labor cost2,70011,000What is the total of the work-in-process account at July 31?

+2
Answers (1)
  1. 23 August, 09:53
    0
    Total Work in process = $68,080

    Explanation:

    Giving the following information:

    On July 1, there were two jobs in process:

    Overhead costs are applied by using a rate of 70% of direct labor costs.

    Job 391 with a beginning balance of $21,700

    Direct materials $5,100

    Direct labor cost $2,700

    Manufacturing overhead = 2700*0.70 = $1890

    Total = 21700 + 5100 + 2700 + 1890=$31,390

    Job 392 with a beginning balance of $8,790.

    Direct materials $9,200

    Direct labor cost $11,000

    Manufacturing overhead = 11000*0.70 = $7700

    Total = 8790 + 9200 + 11000 + 7700 = $36,690

    Total Work in process = total cost Job 391 + total cost Job 392

    Total Work in process = 31,390 + 36,690 = $68,080
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Bryant Company designs and builds fancy dining room tables for individual customers. On July 1, there were two jobs in process: Job 391 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.