Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,400 of direct materials and used $3,900 of direct labor. The job was not finished by the end of September, but needed an additional $2,900 of direct materials in October and additional direct labor of $6,400 to finish the job. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?

+5
Answers (1)
  1. 11 August, 22:52
    0
    Work in process October = $15,700

    Explanation:

    Giving the following information:

    During September, Jaycee Corporation requisitioned $2,400 of direct materials and used $3,900 of direct labor. The job was not finished by the end of September, but needed an additional $2,900 of direct materials in October and additional direct labor of $6,400 to finish the job. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost.

    Work in process = direct material + direct labor + manufacturing overhead

    Work in process = 2,900 + 6,400 + 6,400 = $15,700
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,400 of direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers