Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.40 per machine-hour was based on a cost formula that estimates $192,000 of total manufacturing overhead for an estimated activity level of 80,000 machine-hours.

+1
Answers (1)
  1. 9 September, 10:38
    0
    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base (machine hours)

    Explanation:

    Giving the following information:

    The company's predetermined overhead rate of $2.40 per machine-hour was based on a cost formula that estimates $192,000 of total manufacturing overhead for an estimated activity level of 80,000 machine-hours.

    To allocated overhead costs to a specific job, you need to multiply the estimated rate for the number of machine-hours required for the job.

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base (machine hours)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.