Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $100/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 280 hours at $15/hour? Hint: The hours that the employee works (280 hours) would equate to 7 weeks.

+1
Answers (1)
  1. 24 January, 18:19
    0
    Total cost = $4,900

    Explanation:

    Giving the following information:

    Each member of the project is assigned an overhead charge of $100/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 280 hours at $15/hour? Hint: The hours that the employee works (280 hours) would equate to 7 weeks.

    Total cost = direct labor + allocated overhead

    Total cost = 280*15 + 100*7 = $4,900
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $100/week. What would ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers