Production used 2.5 labor hours per finished unit, and the company actually paid $21 per hour, totaling $52.50 per unit of finished product. What amount is the company's direct labor rate variance for March?

+3
Answers (1)
  1. 2 June, 07:56
    0
    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual hours

    Explanation:

    Giving the following information:

    The production used 2.5 labor hours per finished unit, and the company paid $21 per hour, totaling $52.50 per unit of finished product.

    We weren't provided with enough information to solve the problem. We need estimated production hours and rates. But, I can leave the formula to solve it.

    To calculate direct labor rate variance, we need to use the following formula:

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Production used 2.5 labor hours per finished unit, and the company actually paid $21 per hour, totaling $52.50 per unit of finished ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.