A company identified the following partial list of activities, costs, and activity drivers expected for the next year: Activity Expected Costs Cost Driver Extrusion costs $ 83,600 Number batches made Handling costs $ 8,800 Number of orders filled Packaging costs $ 40,500 Number of units made Product A Product B Production volume 750,000 units 600,000 units Batches made 200 batches 750 batches Orders filled 75 200 Calculate activity rates for each of the three activities using activity-based costing (ABC).

+5
Answers (1)
  1. 18 September, 02:04
    0
    Extrusion = $88 per batch

    Handling = $32 per order

    Packaging = $0.03 per unit

    Explanation:

    Giving the following information:

    Activity Expected Costs Cost Driver:

    Extrusion costs $ 83,600 Number batches made

    Handling costs $ 8,800 Number of orders filled

    Packaging costs $ 40,500 Number of units made

    Product A Product B:

    Production volume: 750,000 units - 600,000 units

    Batches made: 200 batches - 750 batches

    Orders filled: 75 - 200

    To calculate the activity rate, we need to use the following formula:

    Estimated activity rate = total estimated activity costs for the period / total amount of allocation base

    Extrusion = 83,600 / (200 + 750) = $88 per batch

    Handling = 8,800 / (75 + 200) = $32 per order

    Packaging = 40,500 / (1,350,000) = $0.03 per unit
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A company identified the following partial list of activities, costs, and activity drivers expected for the next year: Activity Expected ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.