Ridgeview Mining Inc. agrees to deliver ten tons of coal to Static Energy Corporation. The agreement states that delivery is to be within "9" days, although the parties intend "90" days. Ridgeview cannot convince Static to amend the contract. What remedy should Ridgeview seek from the Courts?

a. damagesb. reformationc. rescissiond. specific performance

+4
Answers (1)
  1. 11 August, 08:45
    0
    Answer: B. Reformation

    Explanation:

    Contract reformation is a legal procedure adopted by the courts to change/rewrite a portion within the contract that truly reflects the intentions of both the parties before they engaged into the agreement.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Ridgeview Mining Inc. agrees to deliver ten tons of coal to Static Energy Corporation. The agreement states that delivery is to be within ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers