Mountain View Company produces hiking boots. The direct labor standard for each pair of boots is 1 hour at a cost of $ 19.00 per direct labor hour. During the month of May, Mountain View Company used 3 comma 000 direct labor hours to produce 2 comma 300 pairs of boots. Total direct labor cost for May was $ 54 comma 000. What is the labor rate variance for May?

+5
Answers (1)
  1. 22 September, 22:28
    0
    Labour rate variance

    = (Standard rate - Actual rate) x Actual hours worked

    = ($19 - $18) x 3,000 hours

    = $3,000 (U)

    Actual rate = Actual direct labour cost

    Actual direct labour hours worked

    Actual rate = $54,000

    3,000 hours

    Actual rate = $18 per direct labour hour

    Explanation:

    Labour rate variance is the difference between standard rate and actual rate multiplied by actual direct labour hours worked. Actual direct labour hours worked is calculated as actual direct labour cost divided by actual direct labour hours worked.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Mountain View Company produces hiking boots. The direct labor standard for each pair of boots is 1 hour at a cost of $ 19.00 per direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.