In spring 2014, Parmac Engineering Company signed a $160 million contract with the city of Parkersburg, to construct a new city hall. Parmac expects to construct the building within two years and incur expenses of $120 million. The city of Parkersburg paid $40 million when the contract was signed, $80 million within the next six months, and the final $40 million exactly one year from the signing of the contract. Parmac incurred $48 million in costs during 2014 and rest in 2015 to complete the contract on time. (Numerical calculations required)

Using the percentage-of-completion method how much revenue should Parmac recognize in 2014? Select one:

a. $40 million

b. $120 million

c. $64 million

d. $80 million

e. None of the above

+4
Answers (1)
  1. 4 September, 07:04
    0
    c. $64 million

    Explanation:

    For computing the revenue recognized, first we have to determine the percentage which is shown below:

    = Cost incurred in 2014 : expenses incurred

    = $48 million : $120 million

    = 40%

    And, the contract price is $160 million

    So, the revenue recognized would be

    = Contract price * percentage

    = $160 million * 40%

    = $64 million
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In spring 2014, Parmac Engineering Company signed a $160 million contract with the city of Parkersburg, to construct a new city hall. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.