Why is it necessary to have a time-phased budget baseline? Select one: a. It allows proper resource allocation b. It reduces schedule slippage when scheduling multiproject resources c. It reduces fluctuations in cash flow during the project d. It shows how much work was accomplished for the money spent e. It is not necessary to have a time-phased budget baseline

+2
Answers (1)
  1. 20 July, 01:55
    0
    Answer:D. It shows how much work was accomplished for the money spent

    Explanation:

    Time phased budget is an approved plan of how much work should be accomplished at stated time on the money spent on a project
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Why is it necessary to have a time-phased budget baseline? Select one: a. It allows proper resource allocation b. It reduces schedule ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers