In a partnership, each member of the project team is responsible for the project's outcomes and the current situation, whether it is positive or shows evidence of project problems. The term that best describes this responsibility is:

A) exchange of purpose.

B) a right to say no.

C) joint accountability.

D) absolute honesty.

+2
Answers (1)
  1. 28 December, 09:19
    0
    The term that best describes the given responsibility is joint accountability.

    Explanation:

    Sharing the responsibilities and the outcomes of any situation in a business entity or firm is known as joint accountability.

    In a joint accountability environment, all the team members plan, decides, delegates and executes the work together. All the members of the team are equally responsible for both the positive and negative outcomes of any project they execute or plan.

    Here, it has been given that in a partnership, each member of the project team is accountable for both the achievements and consequences of the project they are working in. So, we can conclude that the type of responsibility exhibited here is joint accountability.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In a partnership, each member of the project team is responsible for the project's outcomes and the current situation, whether it is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.