WeeBee Company has three assembly labor classifications: S-1, S-2, and S-3. The three classifications are paid $16, $19, and $22 per hour, respectively. The assembly activity for a product uses an S-2 employee who performs that task in 24 minutes. To reduce the activity cost per unit, a product engineer proposes using a higher-rated employee who can perform the assembly in 21 minutes. A manager proposes using a lower-rated employee who can perform the assembly in 30 minutes. Which of the following provides the most cost-effective solution?

A. use the S-1 employeeB. use the S-2 employeeC. use the S-3 employeeD. use either the S-1 or S-3 employee

+3
Answers (1)
  1. 17 June, 22:15
    0
    The answer is: B) use the S-2 employee

    Explanation:

    If you use an S-2 employee to make one unit of the product you are going to spend $7.60 [ (24 min / 60 min) x $19].

    If you use an S-1 employee to make one unit of the product you are going to spend $8.00 [ (30 min / 60 min) x $16].

    If you use an S-3 employee to make one unit of the product you are going to spend $7.70 [ (21 min / 60 min) x $22].

    Using an S-2 employee is the cheapest; $7.60.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “WeeBee Company has three assembly labor classifications: S-1, S-2, and S-3. The three classifications are paid $16, $19, and $22 per hour, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.