A production center is available for 8 hours a day in a factory. It is comprised of several rotary parts, and the worker operating it is required to lubricate these rotary parts regularly each day. It takes 2 hours to remove these parts from the production center, lubricate them, and re-assemble them. The production center is not available for production during these times. What is the availability of the production center?

+1
Answers (1)
  1. 3 April, 16:19
    0
    Total time: 8 Hours

    Lubrication Requirement: Each day

    Time Required for removing, Lubrication. reassembling = 2 Hours

    So Availability of Production Center = 8 hours - 2 hours

    Availability of Production Center = 6 Hours.

    Explanation:

    Production center will not be available for production in the time when rotary parts will be engaged in lubrication process. The rotary parts lubrication will take 2 hours each day.

    So center will be available for production for 6 hours only.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A production center is available for 8 hours a day in a factory. It is comprised of several rotary parts, and the worker operating it is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.