Ask Question
11 October, 20:42

XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000 while the actual overhead cost totaled $265,000. XYZ's estimated direct labor cost was $500,000 and the actual direct labor cost amounted to $510,000. For the current year, overhead was: Group of answer choices

+2
Answers (1)
  1. 11 October, 21:06
    0
    Allocated MOH = $255,000

    Explanation:

    Giving the following information:

    XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000; estimated direct labor cost was $500,000 and the actual direct labor cost amounted to $510,000.

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 250,000/500,000 = 0.5 per direct labor dollar

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 0.5*510,000 = $255,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “XYZ Company applies overhead to jobs using direct labor cost as an activity. For the current year, XYZ's estimated overhead was $250,000 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers