Landen Company uses a single plantwide overhead rate based on direct labor hours. Total budgeted overhead costs are $200,000. Total budgeted direct materials are $50,000 and total budgeted direct labor hours are 80,000. What is the plantwide overhead rate per direct labor hour?

+4
Answers (1)
  1. 13 January, 12:39
    0
    The plantwide overhead rate per direct labor hour is $2.50 per labor hour.

    Explanation:

    Total budgeted overhead costs = $200,000

    Total budgeted direct materials = $50,000

    Total budgeted direct labor hours = 80,000 hours

    Over head rate per labor hour = Total budgeted overhead costs / Total budgeted direct labor hours

    Over head rate per labor hour = $200,000 / 80,000

    Over head rate per labor hour = $2.50 per labor hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Landen Company uses a single plantwide overhead rate based on direct labor hours. Total budgeted overhead costs are $200,000. Total ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.