You are meeting with a customer for initial discussions about a software implementation project. At the end of the day, the customer asks you for a general estimate of the project duration. Based on your experience with three similar past projects you estimate an 8-10 month implementation time frame. What is this type of estimation technique called?

+1
Answers (1)
  1. 27 May, 20:46
    0
    The estimation technique is called comparative or analogous technique. This is because you are making project duration estimates based on previous projects

    Explanation:

    When projections for a current project is based on the outcome and results of past projects, then a comparative estimation is being done.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You are meeting with a customer for initial discussions about a software implementation project. At the end of the day, the customer asks ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers