Ask Question
26 September, 23:32

Which of the following is NOT part of project controlling? A. using a feedback loop to revise the project plan B. close monitoring of resources, costs, quality, and budgets C. sequencing and allotting time to all project activities D. shifting resources to where they are needed most

+5
Answers (1)
  1. 27 September, 00:51
    0
    C. sequencing and allotting time to all project activities

    Explanation:

    This will be part of the Project schedulling phase on which the uhman and materials resources are allocate to complete the activities within the timeframe of the project.

    Asinging time to the project activities is part of the project schedulling phase.

    While within Project controlling are the activities that check how the project is going. It looks for deviation on the expected outcome and notifies to managment. It must ensure the quality, quantity and cost of the goals
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is NOT part of project controlling? A. using a feedback loop to revise the project plan B. close monitoring of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers