Ouzts Corporation is considering Alternative A and Alternative B. Costs associated with the alternatives are listed below:

Alternative A Alternative B

Materials costs

$ 40,000 $ 56,000

Processing costs

$ 37,000 $ 37,000

Equipment rental

$ 13,000 $ 13,000

Occupancy costs

$ 15,000 $ 22,000

What is the financial advantage (disadvantage) of Alternative B over Alternative A?

+1
Answers (1)
  1. 9 June, 00:10
    0
    Answer: Disadvantage of $23000

    Explanation:

    Costs associated with Alternative A:

    40000+37000+13000+15000

    Total cost = $105000

    Cost associated with Alternative B:

    56000+37000+13000+22000

    Total cost = $128000

    To find the advantage/disadvantage we have to find the difference in the costs: 105000 - 128000

    Disadvantage of $23000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Ouzts Corporation is considering Alternative A and Alternative B. Costs associated with the alternatives are listed below: Alternative A ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.