Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?
A. 3.
B. 5.
C. 6.
D. 8.
E. None of the above.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.