Red Raider Company uses a plantwide overhead rate with direct labor hours as the allocation base. Next year, 590,000 units are expected to be produced requiring 0.90 direct-labor hours each. How much overhead will be assigned to each unit produced given the following estimated amounts? Estimated: Department 1 Department 2 Manufacturing overhead costs $ 2,568,000 $ 957,000 Direct labor hours 187,000 DLH 129,000 DLH Machine hours 31,900 MH 9,900 MH

+1
Answers (1)
  1. 8 October, 22:55
    0
    Allocated unitary overhead = $6.64

    Explanation:

    Giving the following information:

    Plantwide overhead rate with direct labor hours as the allocation base.

    Next year, 590,000 units are expected to be produced requiring 0.90 direct-labor hours each.

    Estimated:

    Department 1

    Manufacturing overhead costs $ 2,568,000

    Direct labor hours 187,000

    Machine hours 31,900

    Department 2

    Manufacturing overhead costs $ 957,000

    Direct labor hours 129,000

    Machine hours 9,900

    actual hours of allocation base = 590,000*0.90 = 531000 hours

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate D1 = 2568000/531000 = 4.84

    Estimated manufacturing overhead rate D2 = 957000/531000 = 1.80

    Allocated unitary overhead = 4.84 + 1.80 = $6.64
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Red Raider Company uses a plantwide overhead rate with direct labor hours as the allocation base. Next year, 590,000 units are expected to ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.