Exercise 8-3 Lump-sum purchase of plant assets LO C1 Rodriguez Company pays $405,405 for real estate with land, land improvements, and a building. Land is appraised at $202,500; land improvements are appraised at $67,500; and a building is appraised at $180,000. Required:1. Allocate the total cost among the three assets. 2. Prepare the journal entry to record the purchase.

+2
Answers (1)
  1. 10 August, 11:02
    0
    Rodriguez Company

    Purchase price = $405,405

    Land is appraised at $202,500

    Land improvements $67,500

    Building appraised at $180,000

    Total appraised value $450,000

    Land will be apportioned $202,500/$450,000 x $405,405 = $182,432.25

    Land improvements will be apportioned $67,500/$450,000 x $405,405 = $60,810.75

    Building will be apportioned $180,000/$450,000 x $405,405 = $162,162

    Total cost of assets = $405,405.

    2. Journal Entries:

    Debit Land $182,432.25

    Debit Land Improvements $60,810.75

    Debit Building $162,162

    Credit Cash Account $405,405

    To record the purchase of the assets.

    Explanation:

    The purchase price is proportionately allocated to the items based on their appraisal values.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Exercise 8-3 Lump-sum purchase of plant assets LO C1 Rodriguez Company pays $405,405 for real estate with land, land improvements, and a ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.