A company is interested in monitoring the variability in the weight of the fertilizer bags it produces. An appropriate control chart would be: a p-chart. a c-chart. an R-chart

+1
Answers (1)
  1. 16 August, 07:04
    0
    The correct answer is "R-chart"

    Explanation:

    The R-chart is a model that Indicates how the range of groups changes in a determined line of time. The R-chart is used to control process variability of the group, It is important to clarify that the units to compare, should be 10 or less.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A company is interested in monitoring the variability in the weight of the fertilizer bags it produces. An appropriate control chart would ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.